Ceiling offset

Detail:Ceiling offsetzoom

Place the facing for the vertical slab edge (3) onto the facing for the undeside of the lower slab and stabilize the vertical facing with H20 beams (2). Use a trestle (4) for lateral support and secure it with a beam clamp. Place a timber filler (5) lengthwise onto the H20 beam to gap the height difference to the underside of the upper slab. The horizontal facing for the underside of the upper slab edge must be flush with the adjacent MevaDec panel (1). Support the upper facing by attaching cross-pieces (6) to the trestle and to the groove of the primary beam, one cross-piece every 50 cm. 

 

References

 

MevaDec product page

MevaDec product page

Contact Form

 
 
 

Product List

 
 

Note that each building project will vary in terms of the number of parts needed. If you need assistance in planning the pour, please consult with us via the contact form.

 
 